Harlan Thompson
and Sam Hui
The Malaysian government
is forging ahead with construction of the 2,400-MW Bakun Dam although there
is no proven need for the power. Construction of the diversion tunnels for the
project was completed in April, shortly after Malaysian Prime Minister Mahathir
Mohamed's announcement in February that the project would be revived at its
original size. Some 10,000 indigenous people have been forcibly resettled for
the project and are struggling to survive on resettlement sites.
Despite the latest
construction works, the government has apparently not made a final decision
on the dam. The Sarawak Tribune quoted Sarawak Chief Minister Abdul Taib Mahmud
as saying, "We will proceed with the contracts in stages while waiting
for market conditions to improve...we can make a final and complete decision
on Bakun, maybe by next year."
The project would
cost $5 billion in US currency and flood a tract of rainforest the size of Singapore.
It is being constructed in the remote interior of the Malaysian province of
Sarawak, on the island of Borneo. The dam has been dogged by controversy and
financial troubles since it's inception. When it was approved in 1994, up to
90 percent of the energy created was intended for export to Peninsular Malaysia
via a 650-kilometer submarine cable. The project was shelved in 1997 during
the Asian economic crisis. However, the dam was revived in 1999, in a scaled-back
version.
LACK OF ENERGY
PLANNING
"The manner
in which the Bakun dam has been justified-from the original 2,400-MW with submarine
cable to West Malaysia, to a downscaled 500-MW dam, now back to 2,400-MW without
submarine cable- smacks of very irresponsible policy making. Almost certainly,
no serious attempt has been made to justify the project in terms of energy needs
and supply," said Dr. Kua Kia Soong, director of Malaysian NGO Suaram.

Diversion
tunnels for Bakun Dam
are now complete. However, there is still no light at the end of the
tunnel for SE Asia's largest
infrastructure project.
|
In the latest announcement,
the government claims that the project will supply power to Sarawak and Sabah
provinces. However, Sarawak and neighboring state Sabah currently face a power
surplus, with reserve margins of 54 and 92 percent, respectively. (A reserve
margin indicates how much extra power capacity is available relative to peak
demand.) Furthermore, Dr. Syed Husin Ali, president of the Parti Rakyat Malaysia,
has calculated that if Bakun is completed, the reserve margin of the two provinces
will approach 137 percent in 2006.
The government
hopes to sell the excess energy to Brunei and the Indonesian province of Kalimantan.
However, both Brunei and Kalimantan are oil rich, with plentiful electricity
available at rates much lower than in
Sarawak. Moreover,
there is no electrical transmission infrastructure to these areas. Transmission
between Sarawak and Sabah may prove too expensive to build, as these neighboring
provinces are not yet connected by road. The government hopes that energy intensive
industry will move to the region, however, the dam's remote location and the
likelihood that electrical rates will be prohibitively high may rule this out.
The Bakun Dam revival
comes during an election campaign, with a general election due later this year.
The ruling party hopes the dam will help it win votes by appearing to create
jobs and pump money into the economy.
FUNDING NOT
SECURED
Financing for Bakun
has not yet been finalized. In April, Malaysian newspaper The Sun reported that
Bakun would be financed by up to $2.1 billion in Islamic bonds issued by the
Malaysian Ministry of Finance. The bonds would be raised entirely from the domestic
market and guaranteed by the government. Currently, the government is studying
an offer by Malaysian utility Tenaga Nasional Bhd to take an equity stake in
the project.
In March, Finance
Minister Daim Zainuddin announced that the government would open the project
to bids from foreign companies, particularly in the supply and installation
of electrical equipment and for power transmission work within Sarawak and to
Sabah. French energy company Alstom has expressed an interest in the project.
SERIOUS RESETTLEMENT
PROBLEMS
While project logistics
continue to be developed, thousands of people resettled for the Bakun Dam continue
to suffer at resettlement sites. In 1999, 10,000 indigenous Kenyah and Kayan
people were forcibly relocated from their ancestral homes to make way for the
dam. Most were forced to move to the government-sponsored Sungai Asap resettlement
site, while a few communities moved to other sites or remained on their land.
In the past, the
indigenous peoples subsisted in a self-sustainable economy, cultivating land,
fishing in rivers and hunting in forests. They occupied 70,000 hectares of ancestral
lands. Now, living in poorly constructed longhouses and forced into the cash
economy, unemployment and hunger are prevalent.
Compensation for
people's land has reportedly been paid out, but resettlers claim that the amounts
were inadequate and below market-value. Problems with food security are rising
as cash-poor villagers are unable to grow food on their small plots of mediocre
land. As a result, many villagers have resorted to meals of rice and salt. Alienation
has led to increased alcoholism and violence. In recent months the population
at the resettlement site has since increased 40 percent, further straining meager
resources.
The desperate situation
for people living at the resettlement site threatens to worsen in the next couple
years, particularly as compensation payments run out and the fertility of their
small plots of land drops. It is likely that many will be forced to purchase
expensive fertilizers to cultivate food to feed their families.
Further problems
loom ahead as residents at the resettlement site must pay back government loans
for housing construction. A five-year grace period to begin repayment of the
$13,700 in debt is set to run out in 2003. At that time, families will owe an
average of $80 per month over a 25-year period. The Malaysian government has
offered to reduce payments for families who cannot afford to pay, however, they
will still be required to pay back the loans with interest.
"There is
not much to look forward to these days," said Junis Win, a Kayan farmer
from the Sungai Asap resettlement site. Junis, like many others, is concerned
about the future, particularly how he will pay back the housing loan despite
the fact that he does not have a stable income.
There are still
100-odd families who refused to move to the resettlement site. Instead, most
have chosen to move to the riverside village of Long Buko, further upstream,
with plenty of fish, land for cultivation and forest for hunting. They built
their longhouses from scratch without any help from the state government, which
withheld compensation payments to force people to move to the government-sponsored
resettlement site. The only external help they need is access to basic health
services and formal education for their children. However they remain vulnerable,
since they chose not to move to the official resettlement site and their customary
land is not officially recognized. Residents have reported that a number of
families from the Sungai Asap resettlement site have asked if they could move
to Long Buko.
|